The Client Asked: Can You Launch in Two Weeks? Here's Our Schedule

'Can two weeks work?' We spread the fortnight into 14 cells: 2 for requirements, 5 for development, 2 for integration, 2 for testing, 3 for acceptance and buffer. Yes — with three conditions. The table became a template; integration testing has never been squeezed after a 3-hour production fix.

October 28, 2022Project ManagementSchedulingClient Communication

Q: Can this project launch in two weeks?

A: Don't ask me to promise off the top of my head. Let's spread the two weeks out and count them — you'll see which parts you can help us skip.

Q: How do you spread it?

A: A table. 14 days.

  • Requirements confirmation and prototyping: 2 days. In those 2 days, fields, definitions, and who signs off get locked down.
  • Development: 5 days. Against the confirmed scope, excluding "oh, and one more thing".
  • Integration testing: 2 days. Aligning with your accounts, data sources, and APIs — the most underestimated stretch.
  • Testing: 2 days. One functional pass, one regression pass.
  • Acceptance and buffer: 3 days. Addressing feedback, launch, and some slack.

That's exactly 14 days, with no idle day in between.

Q: So can it be done or not?

A: Yes, with three conditions. One: the scope is finalized today — anything added later goes to the next phase. Two: your materials, accounts, and API contacts arrive on the agreed dates; a one-day slip pushes everything downstream by a day. Three: your acceptance people are available those days — don't save it all for the last night.

Of the three, the second fails most often. On a previous project we waited 4 days on a single Excel file — development had actually finished long before.

Q: What if we absolutely must compress it further?

A: Things can be cut, but be clear about what's being cut. We once did rush a project; what got cut in the end was two secondary pages and one export format — not testing, not the buffer. Cut the 2 testing days, and post-launch rework usually runs past 2 days.

Q: Have you ever compressed something and regretted it?

A: Yes. Once we squeezed integration testing from 2 days into half a day; on launch day we found their API returned a different set of fields in production — one extra nesting level compared to the test environment. It took 3 hours to fix. We have never touched that cell since.

Q: So really, you're negotiating terms.

A: That's right. A schedule isn't a promise — it's the word "two weeks" converted into 14 cells, each with an owner and a fallback when it slips. Once it's spread out, both sides know whether it can be done. That 14-cell table later became a template: next time we discuss a deadline, we just fill in numbers, copy the three conditions verbatim, and skip the argument from scratch.

Consulting · Free initial chat

Need advice for your scenario?

Tell us your business context and current systems, and we'll give an actionable approach.

Contact us

Mon–Fri 9:00–18:00 · We respond on business days within one business day.

WeChat (Business Only)
WeChat (Business Only)二维码

Scan and add our WeChat for consulting

Or fill out the requirements form